M. Sakuntala Devi vs V. Sakuntala And Ors. on 13 December, 1977
State Bank Of India vs H.C.Takyar (Huf) & Ors. on 13 February, 2012
State Trading Corporation Of ... vs Jagdish Gupta on 5 September, 2012
Gauri Shankar Prasad & Ors vs Brahma Nand Singh on 11 July, 2008
Raj Kishore(Dead)By Lrs vs Prem Singh And Ors on 10 December, 2010

User Queries
View the actual judgment from court
Supreme Court of India
Caltex (India) Ltd vs Bhagwan Devi Marodia on 26 September, 1968
Equivalent citations: 1969 AIR 405, 1969 SCR (2) 238
Author: R Bachawat
Bench: Bachawat, R.S.
           PETITIONER:
CALTEX (INDIA) LTD.

	Vs.

RESPONDENT:
BHAGWAN DEVI MARODIA

DATE OF JUDGMENT:
26/09/1968

BENCH:
BACHAWAT, R.S.
BENCH:
BACHAWAT, R.S.
SIKRI, S.M.

CITATION:
 1969 AIR  405		  1969 SCR  (2) 238


ACT:
     Indian  Contract  Act (9 of 1872),	  s.   55--Lease  of
land--Time  as	essence	 of  contract--Intention  if  to  be
clearly stated.



HEADNOTE:
    The	 respondent leased to the appellant a plot  of	land
for  a certain period and stipulated in the lease deed	that
the  appellant	would give notice of renewal  of  the  lease
within a certain  time.	 The  appellant made the request for
renewal	 of  the  lease 12 days after the  time	 fixed.	 The
respondent  asked  the	appellant  to  vacate  the  premises
stating,  that	the  request being made	 out  of  time,	 was
ineffective.   The appellant flied a suit for a	 declaration
that  he  was entitled to the renewal, and stated  that	 the
delay in making the request he excused as (a) it was due  to
oversight;  (b) the respondent had not altered her  position
for  the  worse or to her detriment within the space  of  12
days;  (c) neither party had treated the matter of  time  as
being  as the essence of the transaction; (d) the  appellant
had constructed a service station for petroleum products  of
immense	 utility to the public of the locality; and (e)	 the
appellant  was	in  possession	of  the	 land.	 The   Court
dismissed  the	suit,  and this	 decision  was	affirmed  in
appeal.	 Dismissing the appeal, this Court,		.
    HELD:   The	 lease	fixed  a  time	within	 which	 the
application  for renewal was to be made.  The time so  fixed
was  of essence of the bargain. The  tenant lost  his  right
unless he made the 'application within the stipulated  time.
Equity will not relieve the tenant from the consequences  of
his own neglect which could well be avoided with  reasonable
diligence.
    At	common	law stipulations as to time  in	 a  contract
giving	an  option  for	 renewal of a  lease  of  land	were
considered to be of the essence of the contract even if they
were   not   expressed	 to  be	 so   and   were   construed
conditions  precedent.	Equity followed the common law	rule
in  respect  of	 such  contracts  and  did  not	 regard	 the
stipulation as to time as not of the essence of the bargain,
the  reason being that a renewal of a lease is	a  privilege
and if the tenant wishes to claim the privilege; he must  do
so strictly within the time limited for the purpose. [241 D,
E]
    With  regard to equitable relief against a	failure	  of
the  tenant  to give notice of renewal within the stipulated
time  the  relief   cannot  be given in	 equity	 save  under
special	 circumstances such as unavoidable accident,  fraud,
surprise,  ignorance,, not wilful or inequitable conduct  on
the  part of the lessor precluding him refusing to give	 the
renewal. [241 F]
    Grounds  (b) *and (e) stated for the delay could not  be
regarded as special circumstances.  As to ground (d) it	 was
not  shown  that the service station was of  immense  public
utility.  The fact that the appellant constructed a  service
station was an irrelevant consideration. Ground
     (c)  was not established and it was not shown that	 the
time  was not the essence of the bargain.  As to ground	 (a)
there was  some	 evidence  to show that the delay in  giving
the notice of renewal was due to oversight.  But it was	 not
shown that the delay was due to any unavoidable
239
accident, excusable ignorance, fraud or surprise.  The delay
arose  from  mere neglect on-the part of the  appellant	 and
could have been avoided by reasonable diligence. [242 E]
    Jamshed Khodaram Irani  v.	Durjorji Dhunjibhai, L.R. 43
I.A. 26,   PIrate v. Nicoll [1966] 2 Q.B. 131, 145; Eaton v.
Lyon  3	 Ves  Jun. 690,692; Reid & Anr. v. Grave  &  Ors.  9
LJ.Ch.	24-5, 248, Ram Lal Dubey v. Secretary of  State	 for
India,,	  39 C.L.J.  314  and  Maharani Hemanta Kumari	Devi
v. Safatulla Biswas & Ors. 37 C.W.N. 9, referred to.



JUDGMENT:

CIVIL APPELLATE JURISDICTION: Civil Appeal No. 2347 of 1966.

Appeal from the judgment and decree, dated June 3, 1966 of the Calcutta High Court in Appeal No. 251 of 1965. M.C. Chagla and S.N. Mukherjee, for the appellant. S. V. Gupte, M.G. Poddar and D.N. Mukherjee, for the respondent.

The Judgment of the Court was delivered by Bachawat, ;I. By an indenture of lease, dated February 17, 1954 the respondent leased to the appellant a plot of land at premises No. 22, Jatindra Mohan Avenue, Calcutta, for a term of 10 years commencing from February 1, 1954. Clause 3(c) of the deed provided for a renewal of the lease and was in the following terms :--

"3 (c). The lessor will on the written request of the lessees made two calendar months before the expiry of the term hereby created and if there shall not at the time of such request be any existing breach or non observance of any of the covenants on the part of the lessees hereinabove contained grant to it one renewal of 10 years from the expiry of the said term at the same rent and containing the like convenants and provisos as are herein contained except that as regards the clause for renewal for further period the rent shall be as may be agreed between the lessor and the lessees."

On December 1, 1963, the time fixed for applying for the renewal of the lease expired. On December 13, the appellant made a written request for the renewal. On December 23, 1963 the respondent's solicitors replied stating that the request being out of time was ineffective and asking the appellant to, vacate the land on the expiry of the lease. The appellant had erected structures on the land for the purpose of running a petrol delivery station and was a Thika tenant within the meaning of the Calcutta Thika Tenancy Act, 1949. In February 1964 the respondent filed an application before the Controller asking for eviction of 240 the appellant under ss. 3(vi) and 5 of the Calcutta Thika ,,Tenancy Act. The Controller allowed the application. An appeal from this order was dismissed by the appellate Authority. A revision petition against the order was dismissed by the High Court. While dismissing the revision petition, the High Court stayed the execution of the order of eviction for a month and observed that the authorities under the Calcutta Thika Tenancy Act had no power to decide whether the appellant was entitled to a renewal of the lease. Thereafter the appellant filed the present suit on the Original Side of the Calcutta High Court asking for a declaration that it was entitled to a renewal of the lease, specific performance of the covenant for renewal, an injunction restraining execution of the order of eviction passed by the Controller and for other reliefs. In paragraphs 13 and 14 of the plaint the appellant alleged that the delay in giving notice of renewal should be excused in view of the following special circumstances: (a) the delay was due to oversight; (b) the respondent had not altered her position for the worse or to her detriment within the space of 12 days; (c) neither party had treated the matter of time as being as the essence of the transaction; (d) the appellant had constructed a service station for petroleum products of immense utility to the public of the locality; (e) the appellant was in possession of the land. The respondent contended that the application for renewal being made out of time was ineffective and that there was no ground for excusing the delay. S.P. Mitra, J. accepted the respondent's contention and dismissed the suit. An appeal under clause 15 of the Letters Patent was dismissed by a Divisional Bench of the High Court. Both the courts concurrently held that the letter, dated December 13, 1963 was not a proper exercise of the option by the ,appellant under the lease, dated February 17, 1954 and that there were no special circumstances for excusing the delay in ,giving the notice. The appellant has filed the present appeal after obtaining a certificate from the High Court under Art. 133 ( 1 ) (a) and (b) of the Constitution. The appellant neglected to make the application for renewal of the lease within the stipulated time. Mr. Chagla has submitted that the time is not of the essence of the contract having regard to sec. 55 of the Indian Contract Act, 1877 as interpreted in the case of Jamshed Khodaram Irani v. Durjorji Dhunjibhai(1). Section 55 of the Indian Contract Act provides that "when a party to a contract promises to do a certain thing at or before a specified time, or certain things at or before specified time, and fails to do any such thing at or before the specified time, the contract, or so much of it as has not been performed, becomes voidable at the option of the promisee, if the intention of the (1) L.R. 43 I.A. 26.

241

parties was that time should be of the essence of the contract." In Jemshed's case(1) Viscount Haldane observed that the section did not lay down any principle as regards contracts to sell land in India different from those which obtained under the law of England. It is well known that in the exercise of its jurisdiction to decree specific performance of contracts the Court of Chancery adopted the rule, especially in the case of contracts for the sale of land, that stipulations .as to time were not to be regarded as of the essence of the contract unless they were made so by express terms or unless a clear indication of a contrary intention appeared from the nature of the contract or the surrounding circumstances. In his well considered judgment Viscount Haldane carefully refrained from saying that time was not to be regarded as of the essence in all contracts relating to land.

At common law stipulations as to time in a contract giving an option for renewal of a lease of land were considered to be of the essence of the contract even if they were not expressed to be so and were construed as conditions precedent. Equity followed the common law rule in respect of such contracts and did not regard the stipulation as to time as not of the essence of the bargain. As stated in Halsbury's Laws of England, 3rd ed., vol. 3, art. 281, p. 165 "An option for the renewal of a lease, or for the purchase or re-purchase of property, must in all cases be exercised strictly within the time limited for the purpose, otherwise it will lapse." This passage was quoted with approval by Danckwerts L.J. in Hare v. Nicoll(2). A similar statement of law is to be found in Foa's General Law of Landlord and Tenant, 8th Art. 453, p. 310, and in Hill and Redman's Law of Landlord and Tenant, 14th ed., p. 54. The reason is that a renewal of a lease is a privilege and if the tenant wishes to claim the privilege he must do so strictly within the time limited for the purpose. With regard to equitable relief against the failure of the tenant to give notice of renewal within the stipulated time. the law is accurately stated in Halsbury's Laws of England, 3rd ed.,vol. 23, p. 626, Art. 1329, footnote (u) thus :--"Relief will not be given in equity against failure to give notice in time, save under special circumstances. The decided cases show that in such cases relief is not given in equity save upon the ground of unavoidable accident, fraud, surprise, ignorance not wilful or inequitable conduct on the part of the lessor precluding him from refusing to give the renewal. The limits of the equitable interference in such cases were clearly stated by the Master of the Rolls (Sir R.P.Arden) in Eaton v. Lyon.(3) He observed :- "At law a covenant must be strictly and literally performed; in equity it must be really and substantially (1) L.R.43 I.A.26 (2) [1966] 2 Q.B. 131. 145.

(3) 3 Ves. Jun: 690, 692-3=695-6--30 E.R. 1223, 1224,1225-6.

242

performed according to the true intent and meaning of the parties so far as circumstances will admit; but if unavoidable accident, if by fraud, by surprise or ignorance not wilful, parties may have been prevented from executing it literally, a Court of Equity, will interfere; and upon compensation bei ng made, the party having done everything in his power, and being prevented by means, I have alluded to, will give relief ... I decide this case upon the principles on which, Lord Thurlow decided (Bayley v. The Corporation of Leominster 1792, 1 Ves. 476), and I hope now, it will be known, that it is expected, these covenants shall be literally performed where it can be done; and that Equity will interpose, and go beyond the stipulations of the covenant at law, only where a literal performance has been prevented by the means,-I have mentioned, and no injury is done to the lessor?' We are of the opinion that the stipulation as to time in clause 3 (c) of .the indenture of lease dated February 17, 1954 should be regarded as of the essence of the contract." The appellant not 'having exercised the option of renewal within the time limited by the 'clause is not entitled to a renewal.

The appellant claims relief against the consequences of its default on the grounds enumerated in paragraphs 13 and 14 of the plaint. Grounds (b) and (e) cannot be regarded as special circumstances. As. to ground (d), it is. not shown that the service station is of immense public utility. The fact that the appellant constructed a service station is an irrelevant consideration. Ground (c) is not established and it is not 'shown that the time is not of the essence of the bargain. As to ground (a) there is some evidence to show that the delay in giving the notice of renewal was due to oversight. But it is not shown that the delay was due to any unavoidable accident, excusable ignorance, fraud or surprise. The delay arose from mere neglect on the part of the appellant and could have been avoided by reasonable diligence. As observed 'by the Master of the Rolls in Reid & Anr. v. Grave & Others(1): "The rule is now well established, that no accident will entitle a party to renew unless it be unavoidable. I am of opinion, that nothing but accident, which, could not have been avoided by reasonable diligence, will entitle the plaintiff to a renewal in this Court."

We may add that where no time is fixed for the purpose, an application for renewal for the lease may be made within a reasonable time before the expiry of the term (see Foa's General Law of Landlord & Tenant, 8th ed., article 455, pp. 311-12, Ram Lal (1) 9 L.J. Ch, 245, 248.

243

Dubey v. Secretary of State for India (1), Maharani Hemanta Kumari Devi v. Safatulla Biswas & Ors.(2). In the present case, the lease fixes a time within which the application for renewal is to be made. The time so fixed is of the essence of the bargain. The tenant loses his right unless he makes the application within the stipulated time. Equity will not relieve the tenant from the consequences of his own neglect which could well be avoided with reasonable diligence.

The appeal is dismissed with costs.

Y.P					  Appeal dismissed.